PRINCE2 Foundation Sample exam questions
These questions are not actual exam questions, they are samples for reference.
Which management products is not an output of Starting up a Project?
- Project Brief
- Risk Log
- Issue Log
- Project Organisation
Which role is an optional role in the Project Organisation?
- Project Executive
- Project Manager
- Project Support
- Project Assurance
Which is an appropriate risk response?
- Denial
- Contingency
- Pending
The Customer’s Quality Expectations are first identified in?
- Starting up a Project
- Initiating a Project
- Controlling a Stage
- Managing Product Delivery
Follow On Actions are an output of which process?
- Managing Stage Boundaries
- Controlling a Stage
- Directing a Project
- Closing a Project
Who decides if a Post Project Review Plan should be created?
- Project Executive
- Project Manager
- Project Support
- Team Manager
Who is responsible for communicating the Project Mandate?
- Project Manager
- Project Executive
- Corporate Management
- Project Support
Which is not part of Change Control?
- Change Budget
- Contingency Plan
- Tolerances
Which is an optional plan?
- Project Plan
- Team Plan
- Quality Plan
Who is responsible for the project’s Business Case?
- Project Manager
- Project Executive
- Project Support
The above questions are copyright of HiLogic Project Management 2008 and should not be copied without the written permission of HiLogic Project Management.