Prince2 Foundation - Sample exam questions
Try these Foundation questions to test your understanding of the PRINCE2 method. These questions are based on the 2009 version of PRINCE2. Further sample questions are included in our comprehensive training material. Click here to view a sample of PRINCE2 Practitioner Sample Questions
Which management products is not an output of Starting up a Project?
- Project Brief
- Lessons Log
- Issue Register
- Project Organization
Which of these Project Organization roles does the Project Manager have the option to appoint?
- Project Executive
- Change Authority
- Project Support
- Project Assurance
Which is an appropriate risk response?
- Denial
- Fallback
- Pending
The Customer’s Quality Expectations are first identified in?
- Starting up a Project
- Initiating a Project
- Controlling a Stage
- Managing Product Delivery
Follow On Actions are an output of which process?
- Starting up a Project
- Controlling a Stage
- Directing a Project
- Closing a Project
When should a Benefits Review Plan be created?
- Starting up a Project
- Initiating a Project
- Managing Product Delivery
- Closing a Project
Who is responsible for communicating the Project Mandate?
- Project Manager
- Project Executive
- Corporate Management
- Project Support
Which is set aside to fund likely changes under Change Control?
- Change Budget
- Risk Budget
- Tolerances
Which is an optional plan?
- Project Plan
- Team Plan
- Stage Plan
Which is not optional in a PRINCE2 project?
- Change Budget
- Risk Budget
- Project Assurance
Who is responsible for the project’s Business Case?
- Project Manager
- Project Executive
- Project Support
Click here for a sample of PRINCE2 Practitioner Sample Questions
NEW Sample Foundation Questions!
Which of these PRINCE2 roles needs to ensure the desired project outcome is specified?
- Senior User
- Project Executive
- Senior Supplier
- Project Manager
Which of these PRINCE2 roles should always be carried out by one single person?
- Senior User
- Project Executive
- Senior Supplier
- Project Assurance
Which of these statements are false. Configuration Management is…
- Linked to change control
- Often referred to as Product or Asset Management
- Incorporates the activities of file and document management
- The activity of planning and executing quality controls
Which of these is not a PRINCE2 Process?
- Change Control
- Starting Up a Project
- Managing Product Delivery
- Managing a Stage Boundary
The above questions are copyright of HiLogic Project Management 2009 and should not be copied without the written permission of HiLogic Project Management.
Click here for a sample of PRINCE2 Practitioner Sample Questions
Quick Links
- Upcoming PRINCE2 Training
- Australia - Melbourne:
Foundation & Prac: 15-17 & 19 & 22 Mar - Australia - Perth:
Foundation & Prac: 17-19 & 22-23 March - Asia - Kuala Lumpur:
Foundation & Prac: 12 - 16 April - Australia - Brisbane:
Foundation & Prac: 19 - 23 April - Asia - Kuala Lumpur:
Foundation & Prac: 11-14 & 17 May - UK:
London, Essex, Cambridge...