PRINCE2 Practitioner sample exam questions
The purpose of the following questions are to illustrate the various question style formats within the PRINCE2 Practitioner Exam.
Classical Multiple Choice
Which of the following documents would Project Assurance review to assess the ongoing viability of the project
- End Project Report
- Business Case
- Work Package
- Lessons Learned Log
Yes/No Questions
Column 1 is a list of true and false statements about when a Risk Log is updated. For each of the statements in column 1 select either A (Yes, this correct) or B (No, this is incorrect)
| Column 1 | Column 2 |
| 1. When raising a Highlight Report | A (Yes, this correct) |
| 2. When preparing for an end stage assessment | B (No, this is incorrect) |
| 3. When examining a project issue | |
| 4. When issuing a Work Package |
Multiple Responses
| Identify which of the following are false | |
| 1 |
Project roles can be eliminated for small projects |
2 |
Project Board decision making can be delegated |
3 |
Project Board is accountable for the Project Assurance function, even when delegated |
4 |
Project Assurance and Project Manager roles can be combined |
Matching
Column 1 contains statements about various project situations. Column 2 lists 4 PRINCE2 management products. Review each of the statements in Column 1 and select and select the output in column 2 MOST likely to use the information in the statement. A selection from Column 2 may be used more than once or not at all.
| Column 1 | Column2 | |
1 |
The product brochure is unlikely to be completed for the product launch | A. Risk Log B. Business Case C. Highlight Report D. Project Approach |
2 |
Sales are projected to increase by 5% year on year | |
3 |
25% of the stage’s budget has been consumed | |
4 |
The development of the brochure will be outsourced to a creative agency |
Sequencing
The Chief Executive has approached you to make major changes to the product brochure. In what order would the following likely activities be undertaken?
- Authorisation of actions
- Examine the Project Issue
- Hold an Exception Assessment.
- Record a Project Issue in the Issue Log.
- Produce an Exception Plan.
a) 4, 2, 1, 5, 3
b) 4, 2, 5, 3, 1
c) 2, 4, 1, 5, 3
d) 2, 4, 1, 3, 5
e) 4, 1, 2, 5, 3
Assertion and Reason
Lines 1 to 3 in the table below consist of an Assertion statement and a Reason statement. For each line identify the appropriate selection from options A to E that applies. A selection may be used more than once or not at all.
| Selection | Assertion | Reason | |
A |
True | True | Reason is a correct explanation of the assertion |
B |
True | True | Reason is correct but not an explanation for the assertion |
C |
True | False | |
D |
False | True | |
E |
False | False |
| Assertion | Reason | ||
1 |
Project Assurance should check that the Quality Log is being updated and that quality standards are applied correctly. | Because | Project Assurance is a function of the Project Board |
2 |
Quality assurance should help outline the Business Case. | Because | The quality assurance function should ensure that the project fits with overall company strategy. |
3 |
The Business Case is the responsibility of the project Executive | Because | The project Executive has ultimate responsibility for the project |